Whole Risk Assessment System and Management System of Urban Road Tunnel Operation Stage |
ZHOU Bing1,2, WANG Chuan-sheng1, LIU Fang-liang3, WANG Er-jue3 |
1. Capital University of Economics and Business, Beijing 100070, China:
2. China Communications Construction Co., Ltd., Beijing 100082, China;
3. CCCC Highway Consultants Co., Ltd., Beijing 100082, China |
|
|
Abstract The index system and evaluation method of safety assessment in the operation stage are established to realize the safety risk assessment and management in the operation stage of urban road tunnel. The index scores are obtained from the fuzzy comprehensive evaluation model, and the overall safety risk grade is derived. In view of the index level with an evaluation level greater than or equal to III, special risk assessment is conducted, and safety risk solving measures are introduced. A corresponding safety risk management system platform for urban tunnel operation stage is developed on the basis of the results. The results and application of this study have a certain reference value for managing tunnel informatization based on safety risk management.
|
Received: 21 November 2019
|
Fund:Supported by the National Natural Science Foundation Project (No.U1711265),the Ningbo Major Public Welfare Project (No.2015C110020) |
Corresponding Authors:
ZHOU Bing
E-mail: zhoubingbuaa@163.com
|
|
|
|
[1] Technical Committee 3.3 Road Tunnel Operation, Risk analysis for road tunnels[M]. Paris:PIARC. 2008.
[2] OECD. Safety in Tunnels, Transport of Dangerous Goods Through Road Tunnels[M]. Paris:OECD Publications. 2001.
[3] KRIEGER J, HEIMBECHER F, ZULAUF C. Quantitative Risk Analysis for Road Tunnels[J]. IABSE Symposium Report[J], 2007, 93(4):1-6.
[4] QU X. Quantitative Risk Analysis for Fire in Urban Road Tunnels[D]. Singapore:National University of Singapore, 2012.
[6] KIRYTOPOULOS K A, RENTIZELAS A A, TATSIOPOULOS I P, et al. Quantitative Risk Analysis for Road Tunnels Complying with EU Regulations[J], Journal of Risk Research, 2010,13(8):1027-1041.
[7] WEYENBERGE V B, DECKERS X, CASPEELE R, et al. Development of a Risk Assessment Method for Life Safety in Case of Fire in Rail Tunnels[J]. Fire Technology,2016, 52(5):1465-1479.
[8] ABRAHAMSEN E.B, RØED Willy, JONGEJAN R. A Practical Approach for the Evaluation of Acceptable Risk in Road Tunnels[J]. Journal of Risk Research, 2013, 16(5):625-633.
[9] SAMAD J, LOKE S W, REED K. Quantitative Risk Analysis for Mobile Cloud Computing:A Preliminary Approach and a Health Application Case Study.[C]//Security and Privacy in Computing and Communications (TrustCom), 12th IEEE International Conference on. Melbourne:IEEE. 2013.
[10] Meng Q, QU X, YONG K T, et al. QRA Model-based Risk Impact Analysis of Traffic Flow in Urban Road Tunnels[J]. Risk Analysis:An Official Publication of the Society for Risk Analysis, 2011, 31(12):1872-1882.
[11] SACCOMANNO F, HAASTRUP P. Influence of Safety Measures on the Risks of Transporting Dangerous Goods through Road Tunnels[J]. Risk Analysis:An Official Publication of the Society for Risk Analysis, 2002, 22(6):1059-1069.
[12] NICOLETMONNIER M, GHEORGHE A V. Quantitative Risk Assessment of Hazardous Materials Transport Systems[J], Rail, Road, Pipelines and Ship. 1996, 5(8):1915-1928.
[13] KIRYTOPOULOS K, KONSTANDINIDOU M, NIVOLIANITOU Z, et al. Embedding the Human Factor in Road Tunnel Risk Analysis[J]. Process Safety and Environmental Protection, 2014, 92(4):329-337.
[14] NICOLET-MONNIER M, GHEORGHE A V. Risk Analysis of Hazardous Materials Transportation by Road[J]. Quantitative Risk Assessment of Hazardous Materials Transport Systems, 1996, 5:91-119.
[15] ZHANG J. Risk Assessment Method and Its Application for Shield Tunneling Construction of Cross-River Tunnel[J]. Highway Engineering,2017, 42(1):174-177, 198. (in Chinese)
[16] CHENG Y, ZHU H H, Liu S Y, et al. Construction Risk Assessment of Long-span Shallow-buried Highway Tunnel Based on Fuzzy Theory[J]. Journal of Underground Space and Engineering, 2016, 12(6):1616-1622. (in Chinese)
[17] HU Q F, HUANG H W. Study on Calculation Model of Risk Acceptance Criteria for Tunnel and Underground Engineering[J]. Journal of Underground Space and Engineering,2006, 2(1):60-65. (in Chinese)
[18] YAO X M. Research on Construction Safety Risk Management System of Underground Engineering[D]. Wuhan:Wuhan University of Science and Technology, 2010. (in Chinese)
[19] ZHANG X Z, XIA G M. Project Risk Management System[J]. Engineering Journal of Wuhan University, 2008, 41(6):129-132. (in Chinese)
[20] SU D L, GUO Z Y, ZHOU Y F, et al. Highway Tunnel Operation Risk Analysis and Dynamic Early Warning[J]. Highway Engineering, 2016, 41(6):10-15. (in Chinese)
[21] ZHAO F. Risk Assessment of Highway Tunnel Operation and Research on Fire Escape[D]. Xi'an:Chang'an University. 2010. (in Chinese)
[22] LUO Y, LI Y W, YUAN J W, et al. Study on Safety Risk Assessment of Expressway Tunnel Operation[J]. Modern Tunnelling Technology, 2016, 53(6):25-30. (in Chinese)
[23] ZHAO F, ZHOU Y Q, XIA Y X. Quantitative Risk Analysis Model for Highway Tunnel Operation Stage[J]. Western China Communications Science & Technology, 2010, (5):67-71. (in Chinese)
[24] CJTG H12-2015 Technical Specifications of Maintenance for Highway Tunnel[S]. (in Chinese) |
|
|
|